During Implementation of Planning Central, your client has discovered that no Material Planners have been defined in Manage Material Planners in Planning Central.
In this situation, which three statements are true? (Choose three.)

  • A. You have not been assigned the Materials Planner role.
  • B. Collect Planning Data has not been run for Material Planners.
  • C. Planned Orders will not release successfully.
  • D. The Planner field will be null for all items.
  • E. Your client has not been assigned the Material Planner role.

Answer: C,D,E

 

NEW QUESTION 44
Your client has operations in the west coast of the US. If the customer is in the western half of the US, then they would like to ship the product from their warehouses. If it's in the eastern half of the US, then they want to drop ship it from a supplier.
How would you recommend they set the assignment up?

  • A. Set up by each customer for the customers who should get product from each warehouse.
  • B. Set up two region level assignments, one for the west coast and the other for the east coast.
  • C. Set up an item-organization assignment for the west coast warehouse and an item-organization level assignment for the drop ship.
  • D. Set up a region for the west coast warehouse and an item-region level assignment for the drop ship.
  • E. Set up an item-region assignment for the west coast warehouse and a region level assignment for the drop ship.

Answer: D

 

NEW QUESTION 45
You are setting up the plan page layout for your customer.
In which of these requirements would you use an Infotile?

  • A. Showing on-hand value compared to targets
  • B. Showing inventory value across time
  • C. Showing customer demand trend over a specific time period
  • D. Showing inventory values by product category
  • E. Showing a breakdown of exception in a pie chart

Answer: B

 

NEW QUESTION 46
During the FIFO pegging process, what is the correct order in which the supplies are sorted?

  • A. Pegging process does not respect reservation, and demands are sorted based on due dates
  • B. Peg demands with reservations first and then peg demands that do not have reservations
  • C. Pegging process does not respect reservation, and demands are sorted based on demand and supply types
  • D. Peg unreserved demands first and then demands with reservations
  • E. Pegging process sorts demands by due dates followed by reservation status

Answer: B

 

NEW QUESTION 47
You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?

  • A. The organization must be enabled in Manage Planning Profile Options.
  • B. You do not have data access to the organization.
  • C. The organization must be enabled in Manage Planning Parameters.
  • D. The organization was not enabled for collection under Manage Planning Source Systems.
  • E. The organization is an Item Organization.

Answer: D

 

NEW QUESTION 48
A customer would like to account for the production loss in the supply planning process using the item shrinkage rate planning specification.
Which statement reflects the system behavior to meet this requirement?

  • A. Planning calculation creates scrap demand to compensate for loss and maintains supply.
  • B. Planning calculates no additional demand but creates the additional required supply based on shrinkage factor.
  • C. Planning process reduces the demand based on shrinkage factor and keeps the supply quantity as is.
  • D. Planning calculation does not support shrinkage functionality.

Answer: A

 

NEW QUESTION 49
Where do you view the collected data for Organizations, Customers, Suppliers, Carriers, and Interlocation Shipping Networks?

  • A. View Collected Data
  • B. View Simulation Sets
  • C. Review Plan Inputs
  • D. Planning Analytics
  • E. Maintain Supply Network Model

Answer: E

 

NEW QUESTION 50
You want to check how many items have excess inventory. Where must you go in Planning Central to find this information?

  • A. Configure Exceptions > Expand Supply Planning Exceptions > Select Item With Excess Inventory
  • B. Manage Plans > Edit Demand and Supply Plan > Select Supply tab > Navigate to Item area > Filter by Items with Excess Inventory
  • C. Open Table, Graph, or Tile Set > Search Exceptions > Open > Expand Supply Planning Exceptions > Select Item with Excess Inventory
  • D. Configure Exceptions > Expand Demand Planning Exceptions > Select Item With Excess Inventory
  • E. Manage Plans > Edit Supply Plan > Select Supply tab > Navigate to Item area > Filter by Items with Excess Inventory

Answer: C

Explanation:

 

NEW QUESTION 51
Your customer wants to be able to manually change the input values in purchase orders and transfer orders for the suggested plan recommendations. Which two recommendations are released by supply chain planning to Oracle Supply Chain Orchestration Cloud? (Choose two.)

  • A. New planned orders for make, buy, and transfer of supplies
  • B. Reschedules of sales orders, make, and buy
  • C. Reschedules of existing make, buy, and transfer supplies
  • D. Schedule planned orders for make, buy, and transfer of supplies

Answer: A,C

 

NEW QUESTION 52
Which option outlines changes you can make to a simulation plan when evaluating demand and supply?

  • A. Change item specification values, change item lead times, create mass changes for items all at once, change item-organization specification values
  • B. Add demands, cancel demands, reschedule demands, add supply, cancel supply, reschedule supplies
  • C. Change item specification values, change item lead times, change item-organization specification values
  • D. Change item specification values, change item lead times, create mass changes for items
  • E. Add demands, cancel demands, reschedule demands, add new planned orders, reschedule supplies

Answer: B

 

NEW QUESTION 53
You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.

  • A. In planning measures catalog, shipment forecast measure is not enabled at item and organization level.
  • B. In plan parameters, shipment forecast value measure expression is not defined.
  • C. In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.
  • D. In plan parameters, Item List Price marked as primary does not have price defined for the particular item.

Answer: C

 

NEW QUESTION 54
Which four options can be set as a Demand Schedule in Supply Planning plan options? (Choose four.)

  • A. Approved Final Transfer Order Forecast
  • B. Approved Final Shipments Forecast
  • C. Final Shipments Forecast
  • D. Approved Final Bookings Forecast
  • E. Final Bookings Forecast
  • F. Final Transfer Order Forecast

Answer: B,C,D,E

 

NEW QUESTION 55
You have run a plan for your organization and there were sales orders that have been set up for drop shipment that you cannot see in the plan.
Which two options explain why the sales orders cannot be seen in the plan? (Choose two.)

  • A. Supplier not configured in Manage Planning Source Systems
  • B. Planning Profile 'Enable Planning for Drop Shipments' has not been set to 'Yes'.
  • C. Drop Ship Item Validation Org has not been set up.
  • D. Drop Ship Demand Class has not be set up.
  • E. Include drop ship demands and supplies flag has not been checked on your plan options.

Answer: A,D

 

NEW QUESTION 56
Your client uses product categories and global sourcing rules for supply planning. However, their newest product doesn't follow these rules. For a specific item in the category, it needs to be sourced from a different supplier globally.
How should they set this up for the easiest maintenance, going forward?

  • A. Create a new local sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.
  • B. Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; leave the category as is for the remainder of the products.
  • C. Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; alter the category to be category-organization for the remainder of the products.
  • D. Create a new global sourcing rule for the item; remove the category level assignments and create new item level assignments for all items in the category pointing each to the correct global sourcing rule.
  • E. Create a new global sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.

Answer: E

 

NEW QUESTION 57
A customer has created a supply plan based on current requirement. Due to changes in third party forecast, the plan must be rerun with these recent updates. However, while this new information became available, existing supply like on-hand inventory and work order completions have also been updated.
Which data refresh option should be used to reflect all these changes in the plan?

  • A. Refresh with quick refresh option
  • B. Refresh with selected current data
  • C. Refresh with forecast data
  • D. Refresh with current data
  • E. Do not refresh with current data

Answer: D

 

NEW QUESTION 58
Demand is high leading up to the Christmas holiday every year between Dec 20 and Dec 24 and not on Christmas day (Dec 25). Your customer has two demand plans. Describe the steps to model Christmas causal factor in both demand plans.

  • A. Use FBDI to create a new customer specific Christmas causal factor. Place value of 1 from Dec 20 to Dec 24. Causal factor changes are plan specific, so repeat the steps in the 2nd demand plan.
  • B. Open a demand plan and add a new customer specific Christmas causal factor. Create a table displaying the causal factor measure and relevant time period and modify as required. Causal factor changes in this demand plan will reflect in the 2nd demand plan also.
  • C. Open a demand plan and edit Christmas casual factor measure. Place value of one from Dec 20 to Dec
    24 and zero for non-impacted days including Dec 25. Causal factor changes are plan specific, so repeat the steps in the 2nd demand plan.
  • D. Use FBDI to create a new customer specific Christmas causal factor. Place value of 1 from Dec 20 to Dec 34. Causal factor upload to one demand plan will reflect in the 2nd demand plan also.
  • E. Open a demand plan and edit Christmas casual factor measure. Place value of one from Dec 20 to Dec
    24 and zero for non-impacted days including Dec 25. Causal factor changes in this demand plan will reflect in the 2nd demand plan also.
  • F. Open a demand plan and add a new customer specific Christmas causal factor. Create a table displaying the causal factor measure and relevant time period and modify as required. Causal factor changes are plan specific, so repeat the steps in the 2nd demand plan.

Answer: B

Explanation:
Explanation
References:

 

NEW QUESTION 59
Which two statements are true regarding Planning Business Flows? (Choose two.)

  • A. Inventory Planning cannot run in the Planning Business Flows.
  • B. Demand and Supply Planning have to be run in separate business flows.
  • C. In automated plans, all release rules must be automatic.
  • D. Planners can set up automatic release rules or release orders manually as part of the plan execution.
  • E. You can analyze and adjust data at any stage of the process.

Answer: D,E

 

NEW QUESTION 60
Which release recommendation parameter can you utilize to govern the behavior of the auto-release process?

  • A. Release Only by User
  • B. Auto-Release Planned Order Time Fence
  • C. Auto-Release Interval in Days
  • D. Compression Days Tolerance for Automatic Release
  • E. Quick Release Time Fence

Answer: E

 

NEW QUESTION 61
When planning for customer demand to be fulfilled from internal organizations or from a contract manufacturer, what are the four types of planned orders that can be generated? (Choose four.)

  • A. Transfer orders for internally owned components being transferred from internal organizations to contract manufacturer organizations.
  • B. Buy orders for components purchased at internal organizations and contract manufacturer organizations.
  • C. Transfer orders for internally owned components being transferred from contract manufacturer to internal organizations.
  • D. Return orders for items being manufactured in the contract manufacturer organization.
  • E. Transfer orders for finished goods being transferred from contract manufacturer organizations to internal organizations.
  • F. Make orders for items being manufactured in the contract manufacturer organization.

Answer: A,B,E,F

Explanation:

 

NEW QUESTION 62
You want to be able to filter your data by the planner code attribute on the item. Where can you go to do this?

  • A. The process "Associate Measure Catalog Attributes" must be run to associate new attributes.
  • B. Configure Planning Analytics > Measure Catalog
  • C. The process "Add Levels and Attributes" must be run to associate new attributes.
  • D. Configure Planning Analytics > Levels and Attributes tab
  • E. Enable planner code on Planning Analytics page.

Answer: E

 

NEW QUESTION 63
What happens when a demand planner approves a demand plan and then adjusts shipment history and runs demand plan again?

  • A. The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures
    "not editable." After a forecast is approved, the Final Shipments Forecast and Final Bookings Forecast measures remain unchanged until the forecast is approved again.
  • B. The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures
    "not editable." But any subsequent demand plan run can change Final Shipments Forecast and Final Bookings Forecast values.
  • C. The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. Any subsequent demand plan run can change final shipments or bookings forecast values that will automatically update the approved forecast measures.
  • D. The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. After a forecast is approved, the approved values remain unchanged until the forecast is approved again.

Answer: D

 

NEW QUESTION 64
You ran a demand plan with the data refresh option "Do not refresh with current data." Identify two true statements. (Choose two.)

  • A. Forecasting engine will not run.
  • B. Forecasting engine will run without advancing the plan date.
  • C. Shipments history data will not be modified.
  • D. Shipments forecast data will not be modified.
  • E. Shipments history data will be updated.

Answer: B,C

 

NEW QUESTION 65
You are viewing a drop shipment plan for your organization and you want to know which customer the purchase order will be shipped to. Where can you see that?

  • A. You need to first drill down to the sales order from the supply-demand link, then open the sales order to get the customer.
  • B. You can see the supplier on the sales order, but not vice-versa.
  • C. It is visible in the drop ship analytics.
  • D. You can see the customer on the supply in Supplies and Demand.
  • E. It is not viewable at this time.

Answer: A

 

NEW QUESTION 66
As the planner, you have made some changes to a few of the specifications for items in your simulation sets.
You would like to run one of your existing Demand and Supply Plans that contains this simulation set to see how these changes impact the plan.
Which option shows the steps you must complete in order to ensure that when you run your existing Demand and Supply plan, it contains your changes to the simulation set?

  • A. When the Demand and Supply Plan is run, verify that 'Recalculate Safety Stock' is selected in the Details section.
  • B. You are only able to update one item attribute at a time. Since you have changed multiple attributes, you will be unable to update and run this plan.
  • C. No additional steps are necessary. Any plans that contain your simulation set will automatically be updated with the changes.
  • D. When the Demand and Supply Plan is run, verify that 'Refresh with current data' is selected in the Details section.

Answer: D

 

NEW QUESTION 67
Which four types of supplies can be reserved to a sales order in the inventory? (Choose four.)

  • A. Transfer orders
  • B. Purchase requisitions
  • C. Purchase orders
  • D. Work orders
  • E. On-hand inventory
  • F. Planned Orders

Answer: A,C,D,E

 

NEW QUESTION 68
......

Oracle Planning and Collaboration Cloud 2020 Implementation Essentials Certification Sample Questions and Practice Exam: https://www.itexamsimulator.com/1Z0-1066-20-brain-dumps.html