CIPS L4M8 certification exam is suitable for individuals who work in procurement, supply chain, or operations management roles. L4M8 exam covers a broad range of topics, including procurement processes, supplier selection, contract management, negotiation techniques, and sustainable procurement practices. L4M8 exam also includes questions related to risk management, procurement strategy, and supply chain performance measurement.


To prepare for the CIPS L4M8 exam, candidates are required to complete a series of modules that cover the key concepts and principles of procurement and supply management. These modules are designed to provide candidates with a solid foundation in the subject matter and help them develop the skills and competencies they need to succeed in the profession.

 

NEW QUESTION # 11
In relation to the case study 'Walmart and H&M in spotlight regarding human rights in media ex-plain which human rights are not being granted to the workers.

Answer:

Explanation:
Human rights are the statutory ways in which individual expects to and should be treated. Ethical and responsible sourcing includes the protection of human rights, not violating it.
When young women are being bound into contracts where they work for two to three years, they are not being granted the right to freedom from slavery.
Forcing these women to live in hostels under restrictions that prevent them from moving and are denied the opportunity to improve on their living condition is a violation of their right to life, liberty and personal security, also, their freedom from torture and degrading treatment is being violated.


NEW QUESTION # 12
What is depreciation and deterioration?

Answer:

Explanation:
When an organization want to purchase an asset, it considers the depreciation and deterioration in the whole life of the asset and how it will be manage.
Depreciation is the reduction in value of a tangible and a fixed asset over time. The purpose of calculating the depreciation of the asset is to give the organization a fair and current view of what the asset is worth at a particular time. Depreciation is a way of converting the cost of an asset into an expense over a period of time. Depreciation is a permanent feature listed against an asset throughout its life time and it based on wear and tear, reduction in performance and reduction in value.
Deterioration is the process of something becoming lower in quality or performance. The longer the asset can last without deteriorating the better value the asset represents.


NEW QUESTION # 13
When benchmarking what other factors, apart from price should be considered to find the total cost of acquisition?

Answer:

Explanation:
When evaluating potential suppliers, procurement professionals can carry out benchmarking. Benchmarking is the process of comparing a function, a process performance with another which is best in-class.
Other factors, apart from price that can be considered to find the total cost of acquisition include the product or service quality, lead time, supplier culture, its environmental awareness and sustainability.
Case study:
Tetsuya Tada, Chief engineer of the Toyata Supra Sports car has revealed how the process of benchmarking contributed to the car's design.
Tada has worked by comparing the Supra to other cars. For example, it has been intentionally designed with a shorter wheelbase, than the Toyata 86 to make it more suitable for track racing. Furthermore, Tada has benchmarked the Supra against competition by suggesting that drivers will find the car's performance comparable with that of Posche's Cayman sports car.
Tada's knowledge of the features belonging to different sports cars in his industry shows how benchmarking can be used by companies to successfully differentiate their products and remain competitive through awareness of their competitor's activities.


NEW QUESTION # 14
What effect is technology having on jobs within an organization with which you are familiar with?

Answer:

Explanation:
With the ever developing use of technology, organizations are often under pressure to keep up with numerous technological advances. Jobs could be created in line with technology. Advances in technology can also results in lack of requirement for human impact and as such, jobs could be lost. Though it can help save time and retain bulk files in no space.


NEW QUESTION # 15
What is the method of monitoring suppliers?

Answer:

Explanation:
When a contract has been awarded, either is to meet tangible needs or intangible needs, contractors or suppliers should be managed to ensure that they are meeting up with fulfilling their contractual agreement. To establish this, there are methods of managing contracts and suppliers.
Service level agreement (SLA) clauses: is placed in contract to ensures that supplier meets the expected and agreed level of service Key performance indicator (KPI): are used to manage contracts that fulfill tangible needs, the KPIs are set performance thresholds that are used to monitor supplier's performance.
Management by objectives (MBO): is the process of defining objective that are strategic to the organization relating them to the vision and mission and communicating them to the supplier through the contract and ensuring that this objective is met during contract performance.
Reviews: Regular supplier reviews are good practices, for it gives the buyer opportunity to give feedback on performance.
Continuous Improvement: Contracts and suppliers can be monitored through how they are chang-ing for better incrementally as they are fulfilling the schedule. There must be a set down system to timely improve on the process, people and continuously reduce waste.
Training: It is essential that training, are provided to come up on areas supplier is lacking.


NEW QUESTION # 16
What topics are covered within ethics?

Answer:

Explanation:
Topics that are covered within ethics are;
1. Environmental factors
2. The triple bottom line: profit, people and planet
3. Adopting sustainable practice.
4. considering the social impact of organization's behaviors


NEW QUESTION # 17
Describe three ways in which a buyer could or test the market in other to assist with determining a need.

Answer:

Explanation:
Once the need has been understood, defined, justified and authorized, the next stages are to analyze and test the market. Analyzing and testing the market includes looking at the following
1. STEEPLE analysis
2. SWOT analysis
3. Porter's five forces
4. Level of suppliers competition
5. Supply and demand
6. Push and pull
7. Supplier segmentation
8. Product life cycle
9. Ansoff matrix
10. Early supplier involvement
11. Make or buy
12. Offshoring
1. Porter's five forces: The use of porter's five forces helps the procurement professional to understand the level of competition within the marketplace. Whether it is a monopoly, oligopoly, imperfect or perfect market. Knowing these will equip the organization to better negotiate a favorable price.
2. Supply and Demand: the procurement professional must also think about supply and demand as part of their market analysis when they receive a requisition. This economic factor has a significant effect on the prices charged and on the cost incurred.
3. Supplier segmentation: in this the procurement professional start to form an opinion of potential suppliers.. They can segment current suppliers into four categories, depending on their level of integration into an organization. This can help to inform the procurement professional of which type of supplier relationship that would be most appropriate.


NEW QUESTION # 18
What are the five stages in Tuckman's team Development model?

Answer:

Explanation:
Tuckman's team development model depicts from where a team is formed to the various stages they might experience before the end where the objective is achieved and these includes.
1) Forming: here they are just being put together
2) Storming: conflict and competition begin to arise
3) Norming: here agreement and consensus is reached as roles and responsibility is clear.
4) Perform: They start carrying out the roles and responsibility
5) Adjourning: Task is complete and they are discharged


NEW QUESTION # 19
Which sector most frequently uses invitation to tender?

Answer:

Explanation:
The public sector uses tenders a lot more in the working environment than private sector.


NEW QUESTION # 20
What Incoterm applies here?
The supplier is responsible of placing the goods in the hands of a chosen carrier by the buyer, at which point the buyer takes on the risk.

  • A. EXW - Ex Works
  • B. FCA - Free Career
  • C. CIP - Carriage and Insurance Paid to
  • D. CPT - Carriage Paid To

Answer: B


NEW QUESTION # 21
What does the acronym SMART stand for?

Answer:

Explanation:
When the procurement professional is setting key performance indicator (KPI) where which the supplier performance will be monitored and managed. The KPI is expected to be SMART. SMART is an acronym that is used to set KPI and specification.
S - specific ,
M - measurable,
A - achievable,
R - relevant, and
T - timebound.


NEW QUESTION # 22
What are advantages and disadvantages of the two types of specifications?

Answer:

Explanation:
Ones the need is understood, the procurement professional develops the specifications while working together with stakeholders and colleagues to ensure that the final design is fit for purposes that it meets the generated need.
Specification can be focus on performance or conformance.
Performance specification states what the product or service must do or how it should perform but leave the supplier the freedom to achieve this, however they wish.
Performance specification brings the following advantages; it allows supplier innovation, promote competition in the market place, shorter document, quick to prepare. The disadvantage of perfor-mance specification is that buyers may not know exactly what they will be getting.
Conformance specification gives clear instructions to the supplier about what is required and how it should be achieved. Examples of conformance specifications are chemical formulae, recipes and technical drawings. Conformance specification specifies which standards a requirement must meet or exceed. The advantage of using it is; buyers know exactly what they will get. It has the following disadvantages; the buyer bears the risk, it does not encourage supplier to innovate, take longer and complex documentation.


NEW QUESTION # 23
Using the case study about Toyata, which type of benchmarking Tada has used when comparing the Toyata with Porsche?

Answer:

Explanation:
Benchmarking is the process of comparing a function, process or performance with another which is best-in-class. Benchmarking is either internal or external. External benchmarking has three types; 1) Competition benchmarking, 2) Functional 3) Generic Company Toyota with the Porsche a competition in the same industry and by suggesting that drives will find the cars performances comparable with that of Porsche Cayman sports car, suggest think it is an external competitive benchmark.


NEW QUESTION # 24
What potential costs could an organization face if it fails to conduct Due diligence effectively?

Answer:

Explanation:
Though strong due diligence procurement professionals can assess which suppliers or potential suppliers appear to meet the criteria associated with ethical practice.
Prior to the contract being awarded, strong due diligence can save the organization from the following cost:
1) Cost of reputation
2) Environmental damage
3) Stakeholders dissatisfaction,
4) poor quality and rework
5) Breach of contract
6) Ethical concerns


NEW QUESTION # 25
Describe three ways in which a supplier could improve the effect its company has on the environ-ment.

Answer:

Explanation:
Responsible and ethical sourcing promotes working with suppliers who want to have a positive effect on the environment or at least minimize the damage they cause. Suppliers can make effort to reduce their impact on the planet through reducing the pollution, taking steps to recycle or reuse products can improve on supplier's impact on the environment, also supplier can consider sustainability as another environmental factor. Suppliers with strong values on ethics will have a programme to return anything taken from nature in the form of replanting or replacing.


NEW QUESTION # 26
How does positive social impact present itself?

Answer:

Explanation:
Organizations which display good behavior create a positive social impact. The community in which they are based and to which they supply will benefit from the following.
1. High employment
2. Fair wages
3. low pollution
4. sustainable resources
5. Engagement and movement with local organization


NEW QUESTION # 27
What are the two options for the disposal of an asset if resale is not possible?

Answer:

Explanation:
Disposal of an asset is the final stage in the decommissioning process of a fixed asset.
When a fixed asset reaches the end of its useful or cost effective life time within an organization, the decision is made as to whether it should be removed from the premises or disposed off.
If the asset is truly at the end of its life, no longer fit for purpose, not cost effective to repair and is not able to be exchanged, then disposal is the only option; there are two options for disposal;
1) Take the asset to land fill site
2) Taking the asset to a recycling plant.


NEW QUESTION # 28
Explain how procurement should decide whether to make or buy a product or service.

Answer:

Explanation:
Make or buy decision are about whether a products or services should be made within the organization or bought-in from an external supplier.
For a procurement professional to establish which method (make or buy) offers the best value, the item in question must be thought through if it is core to the organization and which option will add more value to the organization, as regards achieving its strategic goals. If it is core the procurement professional decide to make it and if it is not core the product or services can be bought in.


NEW QUESTION # 29
Describe five types of contract terms that a procurement professional should create with a supplier when forming an agreement.

Answer:

Explanation:
Terms are the right and duties agreed which are then documented in a contract. Five types of con-tract terms that a procurement professional should create with a supplier when forming an agree-ment includes; Price term is when the buying organization wants to protect its budged and spending, it include price terms in the contract, for the buyer to buy goods or services in response to a need they some-time enshrine a bespoke specification in the contract.
Payment Term is to specify when and how the buyer will pay the supplier. The buyer may include a payment term in the contract.
Warrantee is when the buyer requires a promise from the supplier that the product or service will meet the specified need in the contract.
Time is of the essence term is included in the contract to detail when a product or service should be delivered and explains the potential losses of business if time is not observed.


NEW QUESTION # 30
Why is it important to keep ethical codes of practice up to date?

Answer:

Explanation:
A code of ethics is a set of morals and principle set out by an organization to state what it deems to be acceptable conduct and behavior An ethical code of practice is a continually changing and developing document with society changing and different suppliers coming to market, the document has to remain current Suppliers should continually monitor their codes of ethics to ensure that;
1. They are looking after the interest of the supply chain
2. That potential customers can be reassured that they are conforming to the required regulation, e.g. ISO 14001.
Ethical code of conduct should be constantly monitored and updated in accordance with the changes organization faces. This include 1) Define (2) prevent (3) detect (4) reprove (5) evaluate.


NEW QUESTION # 31
What information should be included on a purchase requisition?

Answer:

Explanation:
A purchase requisition should contain the following information
1) Date of the requisition
2) Description of what is required
3) Supplier if known
4) The quantity
5) when the need is required
6) why the need is required
7) who identified the need
8) who approved the need
9) if it's a re-buy


NEW QUESTION # 32
What is contract performance review and continuous improvement?

Answer:

Explanation:
Contract performance review and continuous improvement is the stage 11 of the CIPS procurement and supply cycle.
In order to effectively manage supplier performance and contractual obligations, the suppliers per-formance against key performance indicators (KPI) should be reviewed regularly. This KPI should have been agreed doing the post contract award negotiation. In addition to review KPIs suppliers and the procurement team should work towards continuous improvement. This is a continuous ef-fort to improve product or services within an organization. This may involve improving quality, reducing waste in the supply chain and focusing on innovation. It is an ongoing process that works toward perfection.


NEW QUESTION # 33
Which contract term contains details of when a product or service should be delivered and ex-plained the potential loss of business?

Answer:

Explanation:
Contract terms are the right and duties agreed between parties with which are then documented in contract. Terms can be either implied or expression.
Implied terms are always present in a contract and are set by national laws; like the sales of goods act, whereas express terms are negotiated and created, for example; time is of the essence. When the procurement professional is setting key performance indicators, where which the supplier's performance will be monitored and managed, the KPI is expected to be SMART. The SMART is an acronym that is used to set KPI and specification. It means:
Specific
Measurable
Achievable
Relevant
Time bound


NEW QUESTION # 34
......


CIPS L4M8 Exam is suitable for procurement and supply professionals who want to enhance their skills and knowledge in the field. It is also ideal for those who want to progress to a more senior role in the procurement and supply chain management sector. L4M8 exam covers a wide range of topics, including procurement processes, contract management, and supplier performance management. It also explores the legal and ethical considerations of procurement and supply, making it an essential qualification for professionals who want to work in this field.

 

L4M8 Premium Files Practice Valid Exam Dumps Question: https://www.itexamsimulator.com/L4M8-brain-dumps.html

Practice with L4M8 Dumps for CIPS Level 4 Diploma in Procurement and Supply Certified Exam Questions & Answer: https://drive.google.com/open?id=1vIJm1xcaP5PUeJH1qL3Bxah0dc9B3CYq